Facility Evaluation Report
Licensing Program Analyst (LPA) Dang Nguyen conducted an unannounced Case Management Visit to observe the physical plant. LPA was welcomed by, identified himself to, and discussed the purpose of the visit with Administrator Marcie Laws.
On 09/13/2023, the Licensee submitted an LIC200 Application to the CCLD San Diego Regional Office (RO) to increase the facility's total licensed capacity from forty (40) clients up to forty-two (42) clients. The facility’s floor plan remained unchanged.
On 10/10/2023, the local fire authority approved/granted an updated fire clearance, reflecting the facility was approved for forty-two (42) clients in total, of which ten (10) may be non-ambulatory and none may be bedridden.
During today’s visit, LPA toured the interior and exterior of the day program facility. The facility sketch/floor plan was consistent with the current layout of the facility.
No deficiencies were observed or cited during today's visit.
This portion of the application process has been completed. The Licensee will be sent an updated license to reflect the new fire clearance after CCLD management’s final review and approval.
An exit interview was conducted with Laws, to whom a copy of this report and the Licensee/Appeal Rights (LIC9058 03/22) were provided during the visit.
Source: California Department of Social Services, Community Care Licensing. Methodology · Report a correction