Facility Evaluation Report
On this day Licensing Program Analysts (LPA) M. Yang and R. Bruce arrived unannounced to conduct a POC visit. LPAs met with Staff Enrico Mangunay Yabut. Administrator MaDivina “Grace” Petil was called and arrived shortly.
LPAs received copy of S1 First Aid/ CPR certification with completion date of 08/26/24.
LPAs was informed Administrator schedule appointment for R1 and R2 for TB testing to be completed on 08/29/24. TB result for R1 and R2 shall be submitted to the department by 9/16/24.
1. Non-skid mat in the bathroom tub and shower.
2. Fire extinguisher delivered to the facility on 08/28/24.
An exit interview was conducted. A copy of this report was provided to Administrator, whose signature confirm receipt of report.
Source: California Department of Social Services, Community Care Licensing. Methodology · Report a correction