Licensing Program Analysts (LPAs) Rosaura Valenzuela and Abeye Duguma arrived at the facility on 02/22/2024 at 10:30 a.m. to conduct an announced Pre-Licensing visit and met with Administrator Aaron Khodorkovsky, Entrance interview conducted with the administrator and explained the purpose of today’s visit.
Today's site visit consisted of the LPAs and administrator touring the physical plant at 10:30 a.m. inside and outside the following was observed: The facility has one main entrance being used. The facility is a three floor building. The facility temperature observed to be in the range of 72 to 76 degrees Fahrenheit. The telephone on the premises is operational and functioning. The emergency exit plan/sketch is posted on the walls throughout the building.
Kitchen : At approximately 11:00 a.m. LPAs observed the kitchen area by the dining room to be clean. Appliances observed; sink and refrigerator and stove appeared to be in good repair and functional. The food is prepared at the facility. The food is then placed in large serving trays and transported in a large sealed cart and then individually served to residents at this facility.
Bedrooms: At approximately 11:30 a.m. LPAs inspected fifteen (15) random bedrooms all were observed to be clean and appropriately furnished and equipped with adequate lighting, bedroom furniture and linens. LPA observed the call light system to be on the front desk. Screen doors and window coverings were observed during the time of inspection to be in good condition
Bathrooms: LPA observed bathrooms located inside resident bedrooms to have non-skid shower flooring and appropriate grab bars installed in shower and around the toilet. At 11:50 a.m. hot water was tested in bathrooms and measured at 119.9*F.
Source: California Department of Social Services, Community Care Licensing. Methodology · Report a correction