Senior Care Records.

Facility Evaluation Report

WTC Mosaic Chico, Chico11/30/2023Licence 045920041

Capacity36
Census0
Date signed11/30/2023 01:21:11 PM
The inspector’s account

On 11/30/2023 Licensing Program Analyst (LPA) Jaynae Boyles met with the Administrator Andrea Moriarty

to conduct a Pre-licensing visit. There are currently no participants.

LPA conducted an inspection of the Adult Day Program to ensure compliance with Title 22 regulations. There are four (4) classrooms and two (2) bathrooms for participant use. LPA observed facility to be properly furnished. Bathrooms were in sanitary condition and properly maintained.

LPA checked the kitchen area for the ability to prepare and store food. LPA observed cleaning products and other toxins to be locked away. LPA observed the area used for medication to be locked and inaccessible to residents. LPA observed smoke detectors and carbon monoxide detectors to be operational. Fire extinguisher and first aid kit are maintained and ready for emergency use.

Pre-licensing passed and the Component III is wavied, as this is one three day programs with this agency. Applicant has satisfied all requirements in accordance to Title 22, California Code of Regulations. Application is pending and LPA will forward findings to the Centralized Application Bureau (CAB) for final review and approval. CAB will further contact applicant on final status of application.

Exit interview conducted and a copy of this report was provided to the facility.

Source: California Department of Social Services, Community Care Licensing. Methodology · Report a correction